| Sl No |
Customer´s Name |
Order No and Date |
Brief Description of Job |
Status of Work |
End User |
Project Details |
| 1. |
M/s Thermax Limited Pune |
PO No 772636, 772637 & 772638 dt 19.04.2007 |
Fabrication and Supply of 3 Nos Radiation Casing Hot Oil Heaters for M/s Reliance Industries Limited, Kakinada, A.P. |
Executed |
Reliance Industries |
Refinery of Reliance Industries |
| 2. |
M/s Thermax Engineering Construction Ltd, Pune |
PO No 210721 dt 19.06.2007 |
Erection & Testing of 3 Nos Radiation Casing Hot Oil Heaters for M/s Reliance Industries Limited, Kakinada, A.P. |
Executed |
Reliance Industries |
Refinery of Reliance Industries |
| 3. |
M/s Nicco Corporation Ltd, Kolkata |
C281/W/M/0020 dt 31.08.2007 |
Fabrication, Testing and Supply of Heating coil bundle for Balance Tankage works for M/s Nalco, Damanjodi, Orissa. |
Executed |
NALCO |
Battery E & F, NALCO |
| 4. |
M/s Nicco Corporation Ltd, |
WO No AMD/PS/LOI/C282/481 & 482/07 dt 03.12.2007 |
Fabrication, Erection Testing & Commissioning of Primary Gas Coolers for M/s IISCO, Burnpur, W.B. |
Executed |
IISCO Steel Plant |
Rebuilding of Coke Oven Battery No 10, IISCO Steel Plant |
| 5. |
M/s Mcnally Bharat Engg. Company Ltd, Kolkata |
MBE/KDB/VESSELS/001 dt 18.02.2007 |
Manufacture and Supply of Pressure Vessels for Nalco Evaporation Package, Phase II, Damanjodi, Orissa. |
Executed |
NALCO |
Battery G & H, NALCO |
| 6. |
M/s Mcnally Bharat Engg. Company Ltd, Kolkata |
MBE/KDB/VESSELS/003 dt 18.05.2007 |
Manufacture and Supply of Pressure Vessels for Nalco Evaporation Package, Phase II, Damanjodi, Orissa. |
Executed |
NALCO |
Battery G & H, NALCO |
| 7. |
M/s Mcnally Bharat Engg. Company Ltd, Kolkata |
MBE/KDB/VESSELS/002 dt 17.04.2007 |
Erection of Pressure Vessels for Nalco Evaporation Package, Phase II, Damanjodi, Orissa. |
Executed |
NALCO |
Battery G & H, NALCO |
| 8. |
M/s McNally Bharat Engg. Company Ltd, Kolkata |
06909/NALCO PIPING/ MBE/001 dt 01.10.2008 |
Pre Fabrication, Erection, testing & Commissioning of Pipe Fittings, Flanges, Valves etc for Battery G & H, M/s Nalco, Damanjodi, Orissa |
Executed |
NALCO |
Battery G & H, NALCO |
| 9. |
M/s Shriram EPC Ltd, Kolkata |
KC.05/PO/12/07-08 dt 14.03.2008 |
Manufacture and Supply of SS Static Equipments for ASP Project, M/s IISCO, Burnpur, WB. |
Executed |
IISCO Steel Plant |
ASP Project, Battery 10, IISCO Sttel Plant.
|
| 10. |
M/s Paulwurth India Pvt Ltd, Delhi |
PO No 15100165 dt 05.05.2008 |
Manufacture and Supply of Granulation Tank to BF-3, M/s RINL, VSP, A.P. |
Executed |
Vizag Steel Plant |
Blast Furnace 3 Expn, RINL, Vizag Steel Plant |
| 11. |
M/s Paulwurth India Pvt Ltd, Delhi |
PO No 15100250 dt 14.08 .2008 |
Manufacture and Supply of Feed Tank Closing Plates & Baffle Plates to BF-3, M/s RINL, VSP, A.P. |
Executed |
Vizag Steel Plant |
Blast Furnace 3 Expn, RINL, Vizag Steel Plant |
| 12. |
M/s Shriram EPC Ltd, Kolkata |
KC-04.162(002)/204/039 dt 11.01.2008 |
Design Engineering, Manufacture, Testing & Supply of 100 Cu. Mtr & 30 Cu. Mtr Pressure Vessels for CDI, Bokaro Steel Plant. |
Executed |
Bokaro Steel Plant |
Coal Dust Injection Plant, Bokaro Steel Plant |
| 13. |
M/s Shriram EPC Ltd, Kolkata |
KC.06/PO/26/08-09 dt 22.10.2008 |
Manufacture and Supply of CS Static Equipments to Coke Oven Battery, M/s IISCO, Burnpur, WB. |
Executed |
IISCO Steel Plant |
Coke Oven Battery No 10, IISCO Steel Plant |
| 14. |
M/s Shriram EPC Ltd, Kolkata |
SEPC/KC-10/PGC dt 13.07.09 |
Manufacturing, Supply, Erection Testing & Commissioning of 04 Nos. Primary Gas Coolers to CCD Plant, COB 6, M/s RSP, Orissa. |
Executed |
Rourkela Steel Plant |
New CCD Plant, 7mtr Tall Coke Oven Battery No 6, RSP. |
| 15. |
M/s Shriram EPC Ltd, Kolkata |
SEPC/KC-10/PGC dt 13.07.09 |
Erection, Testing & Commissioning of 04 Nos. Primary Gas Coolers to CCD Plant, COB 6, M/s RSP, Orissa. |
Under Execution |
Rourkela Steel Plant |
New CCD Plant, 7mtr Tall Coke Oven Battery No 6, RSP. |
| 16. |
M/s Shriram EPC Ltd, Kolkata |
SEPC/KC-10/EQPT dt 13.07.09 |
Manufacturing & Supply of SS Static Equipments to CCD Plant, COB 6, M/s RSP, Orissa. |
Executed |
Rourkela Steel Plant |
New CCD Plant, 7mtr Tall Coke Oven Battery No 6, RSP. |
| 17. |
M/s Mcnally Bharat Engg. Company Ltd, Kolkata |
PO No 10007583 dt 08.06.2010 |
Fabrication, Erection, Testing & Commissioning of Pressure Vessels to M/s Utkal Alumina Limited,Tikri, Rayagda, Orissa |
Under Execution |
UTKAL Alumina |
New Battery, Utkal Alumina, Tikri |
| 18. |
M/s Terruzzi Fercalx SPA, Pune |
PO No 5002 dt 25.8.2008 |
Fabrication and Supply of Vertical Shaft Kilns for 2×500 TPD, CRMP Constructions of M/s RINL, VSP, A.P. |
Executed |
Vizag Steel Plant |
CRMP Expansion, RINL, Vizag Steel Plant |
| 19. |
M/s Terruzzi Fercalx SPA, Pune |
PO No 5014 dt 26.2.2009 |
Manufacture and Supply of Burner Peripherals & Cooling Pipes Injectors for 2×500 TPD, CRMP Constructions, of M/s RINL, VSP, A.P. |
Executed |
Vizag Steel Plant |
CRMP Expansion, RINL, Vizag Steel Plant |
| 20. |
M/s Terruzzi Fercalx SPA, Pune |
PO No 6005 dt 27.6.2009 |
Manufacture and Supply of Exhaust Air Piping Assembly for 2×500 TPD, CRMP Constructions of M/s RINL, VSP, A.P. |
Executed |
Vizag Steel Plant |
CRMP Expansion, RINL, Vizag Steel Plant |
| 21. |
M/s Terruzzi Fercalx SPA, Pune |
PO No 6009 dt 18.9.2009 |
Manufacture and Supply of Heat Exchangers for 2×500 TPD, CRMP Constructions of M/s RINL, VSP, A.P. |
Executed |
Vizag Steel Plant |
CRMP Expansion, RINL, Vizag Steel Plant |
| 22. |
M/s Terruzzi Fercalx SPA, Pune |
PO 1446 dt 31.03.2010 |
Manufacture and supply of Gas Piping and Supporting Structures for 2 x 500 TPD, CRMP Constructions of M/s RINL, VSP, A.P. |
Executed |
Vizag Steel Plant |
CRMP Expansion, RINL, Vizag Steel Plant |
| 23. |
M/s Somani Kuttner India Pvt. Ltd., |
VSP-TBM/Buffer Vessel/07-08/03 dt 28.01.2008 |
Manufacture, Testing & Supply of 02 Nos. 100 Cu. Mtr Pressure Vessels for Vizag Steel Plant, Visakhapatnam, A.P. |
Executed |
Vizag Steel Plant |
CRMP Expansion, RINL, Vizag Steel Plant |
| 24. |
M/s Shriram EPC Ltd,Kolkata |
1000004314, dt: 01.03.2011 |
Manufacturing & Supply of CS Static Equipments Oil Precipitator, Emulsion Breaker, Oil Decanter to New CCD Plant, COB 6, M/s RSP, Orissa. |
Under Execution |
Rourkela Steel Plant |
New CCD Plant, 7mtr Tall Coke Oven Battery No 6, Rourkela Steel |
| 25. |
M/s Shriram EPC Ltd, Kolkata |
1000004646 dt 23.03.2011 |
Manufacturing & Supply of Sand Filters to New CCD Plant, COB 6, M/s RSP, Orissa. |
Under Execution |
Rourkela Steel Plant |
New CCD Plant, 7mtr Tall Coke Oven Battery No 6, Rourkela Steel |
| 26. |
M/s Mcnally Bharat Engg. Company Ltd, Kolkata |
PO No 10012683 dt 14.03.2011 |
Fabrication, Erection & Testing of CS/SS/AS Piping & Its Accessories of M/s Utkal Alumina Limited, Tikri, Rayagda, Orissa. |
Under Execution |
UTKAL Alumina |
New Battery, Utkal Alumina, Tikri. |
| 27. |
M/s MECON Limited, Ranchi |
11.51 A 22L/PGC/Pkg No SE 804/8109 dt |
Manufacture, Supply, Erection, Testing & Commissioning of 02 Nos of PGC for RSP, Orissa |
Executed |
Rourkela Steel Plant |
Rebuilding of Baterry 4, Rourkela Steel Plant, Orissa |
| 28. |
M/s UB Engineering Limited, Pune |
J-548/11-12/EPC/035/LOI/01 dt |
Back to Back basis for material receipt, Erection, Testing and Commissioning of CCP 3rd Slab Caster Project of SAIL Rourkela Steel Plant |
Under Execution |
Rourkela Steel Plant |
CCP 3rd Slab Caster Project of Rourkela Steel Plant, Orissa |
| 29. |
M/s ANRAK Alumina
Limited |
PO No: 051:11-12 dt 13.05.2011 |
Detailed Design & Engineering, Manufacture, Testing and Supply of Pressure Vessels (78 Nos.) and Distribution Box (25 Nos.) for ANRAK Alumina Plant, Narsipatnam. |
Under Execution |
ANRAK Alumina |
Battery, Narsipatnam, A.P. |
| Sl No |
Name of Customer |
Brief Description of work |
Work Order No/ Dt |
Job done during the year |
Remarks |
| 1. |
Nicco Corporation Limited, Kolkata |
Fabrication, Erection Works at CFL, Vizag |
C70/P/008 dt 30.07.1992 |
1992 |
Completed |
| 2. |
Nicco Corporation Limited, Kolkata |
Fabrication & Erection Pressure Filters, Pipe etc for JVSL |
C131/W/M/0002 Dt 16.11.1995 |
1995 |
Completed |
| 3. |
Nicco Corporation Limited, Kolkata |
Fabrication, Erection, Testing of Mechanical Equipments & Pipes for JVSL Corex-2000 Module water treatment plant |
C160/W/M/002 Dt 15.07.1998 |
1998 |
Completed |
| 4. |
Nicco Corporation Limited, Kolkata |
Tankage Work at MRL Site Total Piping work for Foam & Cooling System |
C165/W/M/0079 Dt 09.09.1998 |
1998 |
Completed |
| 5. |
Nicco Corporation Limited, Kolkata |
Fabrication & Erection of Piping work for Battery-E of New Evaporation Batteries Project at Nalco Damanjodi. |
C171/W/M/0047 Dt 18.08.1999 |
1999- 2000 |
Completed |
| 6. |
Nicco Corporation Limited, Kolkata |
Execution for Mechanical & Piping Works |
C183/W/M/6012 Dt 28.08.2000 |
2000-2001 |
Completed |
| 7. |
Nicco Engineering Services, Kolkata |
Fabrication, Erection, Testing of Piping and Structurals of Kaiga 3& 4 Projects NPCIL, |
K/WO/C229/04-05/ 006 dt 28.03.2005 |
2005-2006 |
Completed |
| 8. |
Vizag Steel Plant |
Coke Oven Gas Piping for Battery 4, Gas Condensation Plant, RINL, VSP |
VSP/CONT/98/2004 05/6673 & 6674 |
2005-2007 |
Completed |
| 9. |
Hindustan Petroleum Corporation Limited, Visakhapatnam |
Annual Service Contract for Offsite Piping jobs inside Refinery |
M0427C/ 10.7.2007 |
2007 |
Completed |
| 10. |
McNally Bharat Engineering Co Ltd., Kolkata |
Pre Fabrication, Erection, Testing of Pipe Fittings, Flanges, Valves etc for Battery G & H. |
06909/NALCO PIPING/MBE/001 dt 01.10.2008 |
2008 -09 |
Completed |
| 11. |
McNally Bharat Engineering Co.Ltd Kolkata |
Fabrication, Erection and Testing of Piping and its Accessories for UAIL Tikri. |
10012683 DATED 14TH MARCH 2011 |
Job under execution |
Under Execution |
| 12. |
M/s UB Engineering Limited, Pune |
Back to Back basis for material receipt, Erection, Testing and Commissioning of CCP 3rd Slab Caster Project of SAIL Rourkela Steel Plant, Orissa. |
J-548/11-12/EPC/ 035/LOI/01 dt 12.05.2011 |
Job under execution |
Under Execution |